Capital Projects Office
Civic Works Brief
A weekly operating snapshot for the East Channel quay, flood gate retrofit, market pier utilities, and public promenade work scheduled through summer 2027.
Current focus
Flood gate foundations move into night pours
Crews are shifting concrete placement to overnight windows to keep freight access open during the day. The change protects the market pier delivery route while letting inspectors complete the first lift by Friday.
Workstreams
Four sites moving at different speeds
East Channel quay
Sheet pile welding is complete on the north face. Fender bracket layout starts after the survey crew confirms embed plate tolerances.
Market pier utilities
Water service tie-in is ready, but communications ducts require potholing and revised trench protection before heavy excavation returns.
Flood gate retrofit
Foundation pours have the tightest float. Inspection, testing, and cure time now define the critical path for the July hardware delivery.
Public promenade
Landscape mockups are approved. Stone seating and rail lighting can proceed once the temporary pedestrian switchback is striped.
Next milestones
- June 21: Finish first lift inspection and cylinder breaks.
- June 28: Close Pier 3 duct survey and trench protection memo.
- July 9: Council review of contingency draw and traffic control extension.
- July 18: Receive flood gate hardware and begin dry-fit sequence.
Site map
East Channel access plan
Freight, pedestrian, and emergency lanes must stay open while the quay and utility teams work in adjacent zones.